A. The applicant shall, within one year of the date of council interim approval of the PUD site plan, submit a final PUD plan of the proposed development to the zoning administrator, which must incorporate all the changes and conditions required by the council. An appeal stays the decision appealed until a written decision is rendered.

B. The final PUD plan must include reproducible copies of all necessary maps and drawings. The zoning administrator may approve of the final PUD plan if the plan is substantially the same as the interim PUD plan approved by the council and all changes and conditions of the approval have been satisfactorily met.

C. If the final plan is not received within one year of council approval of the interim plan, the approval of the interim plan expires and the applicant may renew consideration of the PUD project only by filing a new application under this chapter.

D. No permit of any nature may be issued by the city relating to the PUD project until the final PUD plans have been approved.

E. No activity or improvements may commence on the site in furtherance of the approved PUD or PUD phase until all construction surety bonds have been posted with and approved by the city, any necessary final plat has been approved and recorded and a notice to proceed has been issued by the zoning administrator.

F. The PUD resulting from application of provisions of this section must be indicated on the official city zoning map and identified thereon by the symbol “PUD” with appropriate reference to the PUD plan and explanatory text. (Ord. 17-007 § 4, 2017)